Mombasa’s capacity race: Berth 19B, Dongo Kundu and the test of growth
Cargo through Mombasa hit a record in 2025. The port’s limit is now capacity, and the projects meant to lift it are real but mostly unfinished.
The Port of Mombasa is East Africa’s main sea gate for cargo moving into Kenya, Uganda, Rwanda, South Sudan and eastern Congo, and for exports leaving the region for markets overseas. In 2025 it had a record year. The practical question for anyone booking a shipment now is whether the port can absorb the next peak without adding days of waiting, and which of the expansion projects will actually be ready.
This article looks at the 2025 figures, the works under way at Berth 19B and Dongo Kundu, and what shippers should watch as the December peak approaches. It is general trade and logistics information, not legal, customs or tax advice. A companion Trade Law Tuesday piece, Where the Customs Line Sits: Berth 19B, Dongo Kundu and the Rules That Follow the Cargo, covers the customs and special economic zone rules around the same projects.
A record year, and a warning
The Port of Mombasa handled a record 45.45 million tonnes of cargo in 2025, up from 40.99 million in 2024, a rise of 10.9 per cent. Container traffic reached 2.11 million twenty-foot equivalent units (TEUs), up 5.5 per cent. Vessel calls rose to 1,955 from 1,873. The figures come from the Kenya Ports Authority (KPA) and were reported by the Kenya News Agency and The Standard.
The growth is not evenly spread. Transit cargo, the freight bound for Uganda, Rwanda, South Sudan and eastern DRC, rose 19.5 per cent to 15.88 million tonnes. Those are growth rates, not shares of the total: Uganda’s transit cargo grew 25.2 per cent, Rwanda’s 22.8 per cent and DRC’s 16.5 per cent, also according to KPA. Import cargo rose to 36 million tonnes from 30 million. Export cargo through the port was much smaller, at 5.03 million tonnes, up only 1.3 per cent from 4.96 million in 2024. Transshipment, the cargo that passes through Mombasa to other ports, fell 22.3 per cent to 385,656 TEUs.
KPA’s chief executive, Captain William Ruto, said the 2025 volume had been projected for 2029 under a 2022 forecast. Early in 2026, the port was congested. He blamed the backlog partly on the elections in Tanzania and Uganda, which he said disrupted cargo transfers, and partly on higher volumes.
Berth 19B: the most concrete project
Berth 19B is a quay extension under construction at Mombasa. It will be 240 metres long with a 15-metre draft, able to take container vessels of up to about 45,000 deadweight tonnes. KPA says it will add about 300,000 TEUs of annual capacity. The project is costed at Sh19 billion.
Progress is the measure to watch. KPA reported the berth about 30 per cent complete in February. By October, Captain Ruto put it at about 56 per cent and said some sections should be released before the end of the year, in time for the December peak. No completion date has been published for the full berth.
Dongo Kundu and the longer build
The larger plan is the Mombasa Special Economic Zone at Dongo Kundu. Its port component is costed at Sh41.1 billion and includes seven berths and yards on 1,300 of the zone’s 3,000 acres. The first multi-purpose berth, 300 metres long, began construction in October 2025. It is scheduled for completion in December 2028 and was about 23 per cent complete in October 2026. Its yard was about 50 per cent complete.
A separate Sh8.3 billion road project, 58 per cent complete in the October reporting, will improve links between the port, Gates 18 and 20, Kipevu Road and the Northern Corridor. Completion is expected in mid-2027.
Systems, and a large private commitment
The digital work is further along than the concrete. A Terminal Operating System upgrade was 40 per cent complete in February. A smart gate at Gate 24 has been completed. A Sh1 billion Vessel Traffic Management and Information System, unveiled in July, now covers three sites, adding real-time vessel tracking, radar surveillance and oil-spill detection. KPA is also buying a search-and-rescue helicopter and three tugboats, valued at roughly Sh1.5 billion to Sh1.6 billion combined.
Private capital is arriving too. In May 2026, at the Africa Forward Summit in Nairobi, the shipping group CMA CGM announced a strategic partnership with Kenya. Trade reporting put the commitment at about €700 million, commonly converted as about US$800 million, or about Sh106 billion, to renovate and upgrade two container terminals at Mombasa. Some later local reports described the same sum as a French government plan. The signed partnership is with CMA CGM, and the figure appears to be one commitment reported in different currencies, not a second pot of money. The reporting still does not name the two terminals or give a completion date, and it does not fully explain how the money is structured.
Is it enough?
KPA’s own long-range projection is that Mombasa will handle at least 50 million tonnes a year by 2050. Reaching 45.45 million tonnes in 2025 suggests that projection is conservative. The port is operating close to full capacity, and much of the 2025 growth came from transit trade, which depends on what happens on the road and at the border after the port gate.
The berths, the road and the terminal systems have to arrive in the same window. A berth that comes online without a clear road to the Northern Corridor only moves congestion. The December peak will be the first real test of whether any early Berth 19B sections actually ease the wait.
What shippers should do now
Book early for the December peak, and treat published transit times as a starting point, not a promise. Ask which terminal and berth the vessel will use, and whether any works or yard limits apply to that call.
If you are importing by sea into East Africa, plan the inland move at the same time as the ocean booking. Extra quay length does not help if the cargo then sits behind a full yard, a blocked gate or a slow border.
If you are exporting from East Africa, confirm cut-offs, yard cut-off times and whether a rolled vessel or a congested stack will still leave enough time for the product, especially perishables moving to markets such as Dubai, London or Guangzhou.
Watch the measures that affect your cargo, not only the capacity announcements: vessel waiting time, port dwell, and the time from gate-out to the border or to the airport for any air on-carriage.
The verdict so far
Mombasa had a genuine record in 2025, and the expansion programme is real. Most of it is still unfinished. Until Berth 19B, the Dongo Kundu works and the road to the corridor are in use together, shippers should plan for a busy port and leave margin in the schedule.
That is the work Sidoman does from Mombasa and Nairobi: air and sea shipments into East Africa, and exports from East Africa to major world cities, including documentation, bookings and coordination through to the destination. If you have cargo to move through Mombasa this peak, talk to us before you book. Follow Sidoman on all platforms for practical trade updates.
Sources
- Kenya Ports Authority, Port of Mombasa Registers Impressive Cargo Growth in 2025: https://www.kpa.co.ke/Media/Read/188
- Kenya News Agency, Mombasa port records growth in cargo volume, vessel traffic in 2025 (29 January 2026): https://www.kenyanews.go.ke/mombasa-port-records-growth-in-cargo-volume-vessel-traffic-in-2025/
- The Standard, KPA steps up Mombasa port expansion as cargo volumes surge (17 October 2026): https://www.standardmedia.co.ke/business/article/2001560312/kpa-steps-up-mombasa-port-expansion-as-cargo-volumes-surge
- The Standard, Mombasa port cargo outperforms forecasts amid lingering congestion (5 February 2026): https://www.standardmedia.co.ke/business/amp/shipping-logistics/article/2001540079/mombasa-port-cargo-outperforms-forecasts-amid-lingering-congestion
- Kenya News Agency, Mombasa Port ramps up expansion, digitisation as cargo volumes rise (13 October 2026): https://www.kenyanews.go.ke/mombasa-port-ramps-up-expansion-digitisation-as-cargo-volumes-rise/
- Kenyans.co.ke, KPA accelerates Mombasa expansion with new berth project (7 June 2026): https://www.kenyans.co.ke/news/124070-kpa-accelerates-port-mombasa-expansion-new-berth-project
- CMA CGM, Africa Forward Summit partnership announcement (11 May 2026): https://www.cmacgm-group.com/en/news-media/africa-forward-summit-rodolphe-saade-signs-government-republic-of-kenya-strategic-partnership-agreement
- Kenyans.co.ke, France to invest Ksh106 billion in Mombasa port terminal expansion (12 May 2026): https://www.kenyans.co.ke/news/123318-france-invest-ksh106-billion-new-mombasa-port-terminal-expansion-kenya
- Maritime Executive, CMA CGM pledges $800 million for Kenya’s Mombasa port (12 May 2026): https://maritime-executive.com/article/cma-cgm-pledges-800-million-funding-to-kenya-s-mombasa-port
- Sidoman, Where the Customs Line Sits: Berth 19B, Dongo Kundu and the Rules That Follow the Cargo: https://sidoman.com/mombasa-berth-19b-dongo-kundu-sez-customs/
Editor’s note: Volumes are KPA-reported figures, as carried by KPA, the Kenya News Agency and The Standard. Capacity and completion figures are KPA projections or progress reports, and several project costs are stated in different sources. The CMA CGM sum is reported as about €700 million, about US$800 million or about Sh106 billion, depending on the outlet and the conversion used. This article is general trade and logistics information, current to 23 November 2026, not legal, customs or tax advice.